Your current browser version is too low, in order to bring you a better browsing effect, please use a higher version browser

Home Products Sport Tennis Centre Steel Structure Space Frame Stadium Roof Project Construction
Sport Tennis Centre Steel Structure Space Frame Stadium Roof Project Construction
Sport Tennis Centre Steel Structure Space Frame Stadium Roof Project Construction
Sport Tennis Centre Steel Structure Space Frame Stadium Roof Project Construction
Sport Tennis Centre Steel Structure Space Frame Stadium Roof Project Construction
Sport Tennis Centre Steel Structure Space Frame Stadium Roof Project Construction
Sport Tennis Centre Steel Structure Space Frame Stadium Roof Project Construction
Sport Tennis Centre Steel Structure Space Frame Stadium Roof Project Construction
Sport Tennis Centre Steel Structure Space Frame Stadium Roof Project Construction
Sport Tennis Centre Steel Structure Space Frame Stadium Roof Project Construction
Sport Tennis Centre Steel Structure Space Frame Stadium Roof Project Construction

Sport Tennis Centre Steel Structure Space Frame Stadium Roof Project Construction

1、The sport tennis center stadium roof project is positioned to serve the needs of mass sports, build a national-level tennis training center, and hold tennis events.

 

2、The main structure of the sports tennis hall is a bolted ball steel space frame, a square quadrangular pyramid, and the support conditions are the peripheral column point support;

 

3、The length and width of the steel space frame of the sport tennis hall is 100.5mX91.5m, the projected area is 9196m², the maximum thickness of the tennis hall is 4.05m, and the facade is wavy, and the top elevation of the space frame is 20m.

 

Technical Advantages

1、In the middle of the steel structure stadium is a tennis court, surrounded by spectator seats. The amount of steel used is about 450 tons.

 

2、Tennis court roof steel space frame installation: Due to the tight construction period, the erection of full-scale scaffolding has a great impact on the construction progress of the project. Therefore, it is considered to adopt the high-altitude bulk construction method as much as possible, so the project quality and safety production requirements are very high.
     The installation sequence of the space frame is carried out from south to north. It is required that the civil construction should reserve a mechanical access channel in the north, and harden the ground in the pavilion to ensure that the car is hoisted on the construction site.