1、At present, the main works of the truss coal bunker are all closed.
2、The construction technology of this coal shed project adopts the cumulative slip method for construction. The computer-controlled hydraulic jacking is used for synchronous sliding, the cumulative sliding distance is 250 meters, and the total weight of the structure sliding is about 4000 tons.
3、The steel structure hoisting in this project has many operations at high places, the site is relatively small, the span of the reticulated shell is large, and the construction is difficult. To this end, the Tongyu Fengcheng Project Department has carefully organized and planned carefully. All management personnel and construction personnel have fought against high temperatures and heat, strictly abided by epidemic prevention and control, actively overcome various unfavorable factors, worked tenaciously, and built a strong safety and quality defense line to ensure The project was successfully completed and met the requirements of Party A.